Committed costs and forecast final cost: why subbies find out about margin loss too late

Reza6 min read

Subbies find out about margin loss too late because most job reports only show what has been paid. Committed cost — orders raised but not yet invoiced — is where the overrun hides. Track budget, approved variations, committed and actual cost on every cost code, and forecast the final cost while you can still act.

Draft.This article hasn’t had its final edit yet, so treat anything specific in it as provisional.

Frequently asked questions

What is committed cost in construction?

Committed cost is money you have agreed to spend but have not yet been invoiced for — mainly purchase orders raised and subcontract packages let. It is a real cost from the day you order, even though it will not reach your accounts until the supplier's bill arrives, which is why reports that ignore it look healthier than the job really is.

What is forecast final cost?

Forecast final cost is your best estimate of what a job will have cost by the time it is finished, cost code by cost code. A common way to build it is actual cost to date, plus committed cost not yet billed, plus what you still expect to spend to complete. Against the budget it shows which codes are over; against the contract sum, the profit remaining.

Why isn't spend to date enough to track a job?

Because spend to date only shows what has been invoiced and paid. Orders already placed, labour already worked and stock already used can all sit outside it for weeks. A cost code can look half spent while it is already fully committed, and the overrun only appears when the last bills land.

How does the estimate become the budget in Subino?

Awarding the job locks the contract to the winning revision, and the budget reads straight from that cost sheet, cost code by cost code. Nothing is re-typed, so the budget cannot drift from the price you won. Changes after that go through variations, so the contract you won stays the contract you won.